A compactor is working on the roadway between the Canada del Buey culvert bridge and N.M. 4. Photo by TK Thompson/ladailypost.com
There has been much progress in the White Rock Victor Center site work and most of the underground utilities are almost complete.
Other site work that is on-going includes: placement of drainage drop inlets, corrugated metal piping in Canada for new driveway and on the RV parking areas.
Placement of masonry block for a dumpster enclosure and cistern tank is scheduled to be completed by the end of this week.
A site retaining wall on the North West corner was poured a couple weeks ago and is currently getting backfilled.
Exterior building sheathing has been completed including metal overhangs.
Metal roofing is scheduled to begin next week.
Plumbing and electrical rough-in is in progress and the installation of the mechanical metal duct is expected to be completed this week.
Looking east over Canada del Buey, workmen in the center of the image are building a culvert bridge over the arroyo for the road connecting the back parking lot of the visitor center to the highway. Photo by TK Thompson/ladailypost.com