Deacon Closed at 15th Monday, Nov. 12

Monday, Nov. 12, the Eastern Area 2 project contractor will be working to install a valley gutter across Deacon at 15th Street.  

Assuming the weather cooperates, the valley gutter will be excavated and concrete should be placed by the end of day Monday.

Once the concrete is finished off, the contractor will place a steel plate across the intersection and reopen the intersection.

The fresh concrete will need to cure for five days. Depending on the weather received over the weekend, the work may be delayed until Tuesday.

Those needing access to Deacon should enter Deacon from 20th Street during the excavation and concrete placement

Contact the Public Works Department at 662-8150 with questions or concerns.