TLC Plumbing and Utility will continue working on Pueblo Drive and 36th Street.
NOTE: Vehicles shall be removed from these roads during construction activities. (7 a.m. to 6 p.m., Monday through Friday)
Construction operations
Pueblo Drive
- Crews will finalize grading the roadway.
- Crews will continue to place curb and gutter.
- Crews will begin to remove drop inlets and install new drop inlets.
36th Street
- Crews will begin to remove drop inlets and install new drop inlets.
- Crews will finalize grading the roadway.
Traffic control
- During construction, road closures, lane restrictions, and detours will be in place.
- Follow all work zone signs and exercise caution.
- Access to residents will be maintained.
Questions and concerns
- Contact the Public Works Department at lacpw@losalamosnm.gov or call 505.662.8150
- Department of Public Utilities at CustomerCare@losalamosnm.gov or call 505;662.8333
- For additional project details, visit the webpage: Denver Steels Phase II Improvements Project
9th St. Sidewalk Improvement Project
- Franco Builders is continuing construction on the east side of 9th Street.
- NOTE: Vehicles must be removed from 9th St. during construction activities. (7 a.m. to 6 p.m., Monday through Friday)
Construction operations
- Construction activities are from Central Avenue to the Central Park condominium entrance.
- Remove approximately 200 feet of deteriorated sidewalk and 74 feet of curb and gutter, properly dispose of all associated debris.
- Continue forming the new curb along the east side of the street through to Central.
- Place and compact base course material for the curb, gutter, and sidewalk installations.
- Pour and finish concrete for the curb, gutter, and sidewalk.
Traffic control
- During construction, road closures, lane restrictions, and detours will be in place.
- Follow all work zone signs and exercise caution.
- Access to residents will be maintained.