Cone Zone: Week Of April 5, 2021

COUNTY News:

The projects listed in this section are being managed by County Public Works staff through contractors.

For more information, email lacpw@lacnm.us, call 505.662.8150, or visit the “Projects/Public Works” link at www.losalamosnm.us.

Please slow down and use caution within the construction work zones. Please note the below information is based on a schedule provided by the contractors and may change due to weather or other delays.  

Public Works Projects: 

Canyon Rim Trail Underpass 

AUI, Inc. of Albuquerque will continue work to construct the Canyon Rim Trail Underpass. The project includes extension of the 10 ft. wide hard surface trail connecting the terminus of the Canyon Rim Trail and existing trailhead to Entrada Drive beneath NM 502 via a reinforced concrete box structure.  

Due to the amount of construction activity that includes trenching, excavation and utility relocation near the trailhead, the trailhead parking lot and a 100 ft. section of the trail near the trailhead will be closed for safety. During this week’s construction, crews will be working along the westbound and eastbound shoulders of NM 502 to clear and remove vegetation, but no vehicular travel lanes will be impacted at this time. AUI will be hauling excess material from project site to a site off DP Road. They will be using end dump trucks to haul excess material. Traffic signs and devices will be installed. Motorists, bicyclists, and pedestrians and are advised to stay alert for construction personnel and equipment and use caution traveling through the work zone. 

ADA improvements along Trinity Drive from Oppenheimer to 39th Street 

Beginning Monday, crews with GM Emulsion will restart construction of pedestrian and ADA improvements along Trinity Drive from Oppenheimer to 39th Street. Late last year, crews completed similar work on the north side of this segment of Trinity Drive. Comparable improvements are now scheduled for the southern side which include replacement of damaged curb, gutter, and sidewalks.  

Work is scheduled 7 a.m. to 5 p.m. Monday through Friday, weather permitting. Traffic signs and devices will be installed to shift vehicular, bicycle and pedestrian traffic around the work zones. Access to residents and businesses as well as services such as mail delivery, emergency services, trash and recycling collection will be maintained. Motorists, bicyclists, and pedestrians and are advised to stay alert for construction personnel and equipment and use caution traveling through the work zone. 

Barranca Mesa – Warranty Work 

TLC Plumbing and Utility will conduct construction activities beginning April 5 and continuing through Monday, April 12. Contractor will be working on Tecolote and Camino Encantado.  

The contractor will coordinate with residents when removal of vehicles from their street will need to take place. Work hours are 7 a.m. to 4 p.m., Monday through Friday.

Services such as mail delivery, trash and recycling collection and emergency services will be maintained. 

Kiddie Pool/ Multi-Generational Pool Construction (addition to Aquatic Center) CGI will be hauling excess material from the project site to a site off DP Road. The shoulder is closed on the north side of Canyon Rd next to the Aquatic Center. In addition, the sidewalk next to the Nature Center is closed on the north side of Canyon Road. These closures are expected to continue throughout construction, until the completion of the project in early 2022. 

Traffic & Streets Division Projects: 

The projects listed in this section are being conducted by County Traffic & Streets crews. For more information, please e-mail lacpw@lacnm.us, contact Scott Halder, Streets Superintendent with questions or concerns at 505.412.7854. Please slow down and use caution within the work zones. Please note the below information may change due to weather or other delays.  

Range Road Shoulder Work

Crews will be working on clearing and repairing shoulders on Range Rd while using a flagging operation Monday through Friday, beginning at 9 a.m. and ending at 3:30 p.m. each day. 

Spring Cleaning on Canyon Rd., Trinity Drive, and Diamond Drive

Crews will be cleaning out islands, sidewalks and handicap ramps Monday through Friday 8:30 a.m. to 3:30 p.m. This work will be accomplished with a street sweeper and no closures are anticipated. Be observant of activities around the sweeper and proceed with caution traveling around the equipment.

Dept. of Public Utilities Projects:

The projects listed in this section are being managed by the County’s Dept. of Public Utilities staff through contractors. For more information, contact the Customer Care Center, Monday through Friday, from 8 a.m. to 5 p.m. at 505.662.8333 or email CustomerCare@lacnm.us

Planned Asphalt and Concrete Repairs – Various locations

GM Emulsion crews will continue repairs to emergency utility asphalt and concrete cuts that occurred during the winter. Crews will rotate to various locations throughout the Los Alamos and White Rock neighborhoods throughout the month of April. Some minor traffic delays are expected.

Traffic control equipment, such as signage, barrels and barricades will be erected around the work zones. Flagging operations may be deployed to assist with traffic flow. Crews will begin at 8 a.m. and work until 5:00 p.m. Most locations slated for repairs are on residential streets and should not take more than two to three days. Traffic impacts should be minimal. Motorists are advised to use caution and pay close attention to signage around the work zone. 

Non-County Projects:

The following road construction updates are posted below in the interest of keeping residents informed, but are being managed or conducted by others. Please obey all traffic devices and slow down in work zones. Please direct questions or concerns to the project contact listed below:

Traffic Alert! Lane Shift to North Side of NM502 starts Monday for Roundabout Project 

Beginning Monday, east bound traffic east of the Round-About will be shifted to the north side of NM 502 and channeled back into the east bound lane in front of the Crossroads Church. This is necessary to demo and build and the remaining south side of NM 502. The traveling public is advised to exercise caution while traveling through this area.

Canyon Road will be closed at First Street and the intersect of W. Manhattan Loop and Canyon Road. Access to the affected residence will be accommodated accordingly. This closure is necessary to demo and build the new alignments of Canyon Road and Manhattan Loop.

Arroyo Lane will be required to access NM 502 on the north side with east and west bound traffic. A STOP sign will be in place at that junction with NM 502. Those motorists are encouraged to pay attention to the traffic control signage.

Motorists are reminded the posted speed limit through the project is 25 MPH.

R and M Construction – 1010 Central Ave., Sidewalk Closure

Sidewalk access on the north side of Central Ave from 1000 Central Ave. to the entrance to the Bradbury Museum complex will be closed to pedestrian traffic starting Monday and will continue through April 30. Pedestrian traffic will be detoured to the south side of Central Ave at Knecht Street. Pedestrian traffic will then be detoured at the intersection of Central Ave and 15th to the north side of Central Ave. Contact: Robert Sanchez 505.927.2027.

Marcon Excavating – Arkansas Ave Road Utility Infrastructure Replacement

Arkansas Ave between Diamond Drive and 41st Street will be closed to through traffic until May 17 while crews replace existing water and sewer lines and connect to County infrastructure for Arkansas Place and the new townhomes being constructed. Contact: Kris Luster 505.690.0587.

DP Rd (Work related to Canyon Walk Apts and The Bluffs – Bethel Development) Qualcon Builders, LLC – 120 DP Road Utility Infrastructure Replacement and Roadway Reconstruction

Next week, trenching activities for the storm drain installation will impact the segment of DP Road east of the Canyon Rim Trail crossing to Fire Station #2 with the roadway restricted to one-lane traffic controlled by a flagged/signaled system. One lane traffic restrictions will occur only during hours of construction potentially 7 a.m. to 7 p.m. daily. Access to businesses will be maintained during these activities. 

The contractor is working in the right-of-way to replace existing utilities with upgraded services related to the new Canyon Walk Apartments (under construction) and The Bluffs senior housing (soon to be constructed). After completion of the storm drain work, the roadway reconstruction, including installation of curb and gutter, and sidewalks will begin with the final paving being the last activity. All construction activities related to the reconstruction of DP Road are expected to be substantially completed by the end of April. Direct questions/concerns to Public Works Liaison Keith Wilson at 505.231.3961.

Other Resources: 

Construction updates are posted at www.losalamosnm.us each Friday explaining traffic control to be expected for the following week – link to News/The Cone Zone. Or, subscribe to The Cone Zone newsletter and receive automatic traffic updates via e-mail each week – just visit the “Newsletters” link on the home page and click on “The Cone Zone” subscribe box.