Shallow Communication Line Uncovered on 15th Street

Due to uncovering a shallow Century Link communication line, the concrete work on the 15th Street road project scheduled for this past week has been delayed. North Sage at 15th Street remains closed through Tuesday, Sept. 10 to allow fresh concrete to cure. North Oakwood Loop at 15th remains closed through Tuesday, Sept. 10 to allow fresh concrete to cure. Nectar Street at 15th Street is closed for the installation of concrete pavement on the east end of Nectar adjacent to 15th Street. The work zone encompasses the easternmost 75 feet of Nectar. This intersection will reopen no later than Friday, September 20. All other access points to and driveways on Nectar remain open. Photo by Carol A. Clark/ladailypost.com

Photo by Carol A. Clark/ladailypost.com